• Skip to primary navigation
  • Skip to main content
  • Jobs
  • Pressroom
  • MyTTI
  • Contact Us
  • Facebook
  • Twitter
  • LinkedIn
  • YouTube
  • Instagram
  • SlideShare
  • RSS

Texas A&M Transportation Institute

Saving Lives, Time and Resources.

  • About TTI
    • Overview
    • Academic Partners
    • Advisory Council
    • Hall of Honor
    • History
    • Sponsors
    • Participate in Research
  • Focus Areas
    • Connected Transportation
    • Economics
    • Environment
    • Freight
    • Human Interaction
    • Infrastructure
    • Mobility
    • Planning and Operations
    • Policy
    • Safety
    • Security
    • Workforce Development
  • Facilities
    • Connected Transportation
    • Infrastructure
    • Safety
    • Environment
    • Traffic Operations
    • Maps
  • Home
  • Centers
    • National
    • State
    • Research Internships
  • People
    • People Search
    • Directory
  • Publications
    • Catalog Search
    • Texas Transportation Researcher
Home / Publications / Catalog Search / Assessing the Costs Attributed to Project Delay During Project Pre-Construction Stages

Assessing the Costs Attributed to Project Delay During Project Pre-Construction Stages

Full-Text PDF

Author(s):

C.P. Beaty, D.R. Ellis, B.A. Glover, W.R. Stockton

Publication Date

March 2016

Abstract

This project for the Texas Department of Transportation developed a simple but sound methodology for estimating the cost of delaying most types of highway projects. Researchers considered the cost of delays during the pre-construction phases of project development: planning and scoping, preliminary engineering, final design, and letting. Researchers developed a simplified model that incorporates 16 user-controlled variables and produces estimates of the effect of project delay on personal and commercial travel and the cost to the general economy. While the methodology is simple, there is no rule of thumb because project delay costs depend on several variables, primarily location, traffic, construction costs, and travel speeds.

Report Number:

0-6806-FY15 WR #3

Keywords:

Contractor, Cost, Delay, EA, EIS, FONSI, HCI, Highway Cost Index, Letting, Permitting, PS&E, Scope

Link(s):

Document/Product

http://tti.tamu.edu/documents/0-6806-FY15-WR3.pdf

Publication/Product Request

TTI reports and products are available for download at no charge. If an electronic version is not available and no instructions on how to obtain it are given, contact the TTI Library.

  • The State of Texas
  • Texas Homeland Security
  • Texas Veterans Portal
  • State Expenditure Database
  • Statewide Search
  • State Auditor’s Office Hotline
  • TAMUS Risk, Fraud & Misconduct Hotline
  • Site Policies
  • Open Records Policy
  • Statutorily Required Reports
  • TTI Rules
  • Veterans
  • Equal Opportunity
  • COVID-19 Info
  • Jobs
Member of the Texas A&M University System

© 2025 Copyright Statement / Legal Notices and Policies

Comments, suggestions, or queries? Contact us!

Texas A&M Transportation Institute · 3135 TAMU · College Station, Texas 77843-3135

(979) 317-2000